title: "Revitalisation of Prague’s Kampa Park to Begin in March 2027 – Park to Remain Accessible"
description: "Prague’s Kampa Park will undergo extensive revitalisation from March 2027. The park will remain accessible to pedestrians, but lawns will temporarily…"
url: "https://www.praguedaily.news/2026/11/25/revitalisation-of-prague-s-kampa-park-to-begin-in-march-2027-park-to-remain-accessible/"
published: "2026-11-25T09:41:00+01:00"
updated: "2026-11-25T09:45:50+01:00"
author: "Prague Daily News editorial team"
section: "News"
---

# Revitalisation of Prague’s Kampa Park to Begin in March 2027 – Park to Remain Accessible

The main work on the paths and green spaces is expected to be completed by the end of May 2027

**The popular Kampa Park in the heart of the Czech capital is set to undergo extensive revitalisation from March 2027. Despite the planned construction work, the park will remain accessible to pedestrians. However, the lawns will be temporarily closed.**

According to the current schedule, the revitalisation of Prague’s Kampa Park is set to begin in March 2027. The main work on the paths and green spaces is expected to take around three months and is scheduled for completion by the end of May.

The project includes the renovation of existing paths and the creation of new ones, extensive landscaping work and the installation of new railings along the Čertovka branch of the Vltava River. The park’s basic layout and original character will be preserved.

“Kampa will remain accessible throughout the construction period. Access to local facilities and businesses will also be maintained. The main paths and lawns are expected to reopen by the end of May 2027, allowing people to enjoy the park as usual during the summer despite the ongoing finishing work,” explains Mayor Terezie Radoměřská.

![Visualisation: Studio TAK](https://pub-94d1cc15a07543a1a84d2eef096b8d24.r2.dev/content/03-130-park-kampa-0005-scaled-1789621513145-ax3ymw-lg.webp)

Visualisation: Studio TAK

#### Work to Begin Along the Čertovka

The first phase of construction, lasting around 45 days, will focus on the paths along the Čertovka and the two connecting paths. A section of the path between the Werich Villa and the Sova Mills (Sovovy mlýny) is also set to be renovated. Particular attention will be paid to protecting the existing trees.

Work on the main path is scheduled to begin in mid-April. This will be followed by the installation of new park furniture and work on the children’s playground.

Alongside the renovation of the paths, the green spaces will be redesigned. The lawns will therefore be temporarily closed from March. However, the Odkolek Garden and the Nostitz Garden will remain accessible throughout the revitalisation.

![Visualisation: Studio TAK](https://pub-94d1cc15a07543a1a84d2eef096b8d24.r2.dev/content/02-130-park-kampa-0006-scaled-1789621472707-c6whua-lg.webp)

Visualisation: Studio TAK

#### New Park Lighting and Sustainable Construction

The park’s lighting is already being replaced with lamps in the style of traditional Prague lanterns. The capital is covering the entire cost of replacing the lighting. Most of the work is expected to be completed by the end of 2026.

When renovating the park’s paths, the city district is focusing on sustainability. Up to 75 per cent of the existing path materials are to be reused. This will reduce both costs and the number of lorry journeys through the park and surrounding streets.

The legally binding conclusion of a review procedure concerning the public procurement process [paved the way for the revitalisation in September](https://www.praguedaily.news/2026/09/17/revitalisation-of-prague-s-kampa-park-can-start/) 2026.

Prague’s first city district will provide updates on the progress of the construction work and any potential restrictions on its official website and on information boards directly in the park.